More beams, more debris

In 2526, there was major progress installing the overhead beams and (on top of them) the plywood flooring that allows scaffolding to be erected so that work can progress on the upper floors. By week's end, new beams had been installed in the front section of the building from the first to the fourth floor, and plywood had been laid on the fifth floor.
The photo above shows preparations for beams to be installed on the second floor of 2526.

This week the last pile of debris was pushed down to the first floor of 2524 from the top floors of the building. Three workers carried this mess outside in one workday.
The sign on the rubbish heap asks "Where will you spend eternity?" It appeared with the debris that was swept down from above.
This was the way the area pictured above looked at the end of the work week.

With the debris removed...

Our former church building has been boarded up and filled with rubble for so many years that it can be both surprising and heartwarming to discover what is visible now that the debris is getting cleared out.

Below is the interior view of the the entrance into the church (from the street).



Directly inside the entrance is a gaping hole that spans approximately a third of the width of the building.

This is the view into the back (public) hallway. We used to go through here to reach our Sunday School/Head Start classroom. Do you remember the distinctive green paint on the door leading to the outside?

New beams!

Removal of debris continued during the third week of work. By Friday, July 18, two major milestones were reached: New beams had been installed in the front part of the first floor of 2526, and debris had been pushed down and removed from all four floors above the front part of 2524.

The steel beams—structurally sound components of the original sturdily-built building—were painted, and new beams were installed.

This photo was taken from the roof of our building at 2522 Adam Clayton Powell Jr Blvd (formerly Seventh Avenue), looking down into the work site at 2524. During this third week of the gut renovation phase, debris from the second floor/front was moved downstairs and carried out to the dumpsters; then debris from the third floor/front was moved downstairs and carried out to the dumpsters; then debris from the fourth floor/front was moved downstairs and carried out to the dumpsters; then debris from the fifth floor/front was moved downstairs and carried out to the dumpsters. By Friday afternoon, the structural "bones" of this area were finally visible.

Before renovation could begin...

This was what we encountered when the the buildings were opened in February of 2006 for the stabilization phase of work to begin.



At day's end, Friday, July 11

From the doorway at 2524, one of the commercial dryers from the former laundromat is visible among the remaining debris.

Next door, plywood now covers the gaping holes in the floor. This is the space that served as the original sanctuary of Seventh Avenue Mennonite Church and was the first classroom for our Head Start program.

Gut Renovation Begins!


On July 3rd, the contractors and the containers arrived outside our buildings to begin the "gut renovation" phase of the Joshua Plaza building project. News traveled quickly because we have been waiting, working and praying for this day for so long! (The fire that destroyed 2526 and 2524 Seventh Avenue took place in October 1974.)

The photo above was taken on the morning of July 10, when four workdays had already been completed.