For many months at the start of demolition and construction, the only way to get above the first floor was to climb a ladder—and depending how far/where you wanted to go, perhaps also out a window and up a fire escape. Now there is an actual stairway—not just the poured concrete stairs that were themselves so exciting several months ago. The elevator shaft also has been built. The photograph directly above shows parts of the elevator track mechanism awaiting installation.
A long way from ladders
For many months at the start of demolition and construction, the only way to get above the first floor was to climb a ladder—and depending how far/where you wanted to go, perhaps also out a window and up a fire escape. Now there is an actual stairway—not just the poured concrete stairs that were themselves so exciting several months ago. The elevator shaft also has been built. The photograph directly above shows parts of the elevator track mechanism awaiting installation.
After the front walls, the stoops
...and the (front) wall came a tumblin’ down!
Salvaging a symbol
Our contractor is very accommodating about requests that might seem silly to some people. Monroe asked for the glass blocks that formed the cross above the original door (see photo below) to be removed intact and turned over to him so that they can be incorporated somewhere in the new sanctuary. The blocks that had already come out at the time this photo was taken have already been put aside.
Changes inside and out
The apartments are being framed, and plumbing and electrical lines are being run. The fire escapes at the rear of the building have been replaced. And with the completion of the concrete stairways, there is no longer a need to climb in and out of windows and up and down the fire escapes for access to the upper floors!


Scaffolding and Sheds
When scaffolding suddenly appeared in February 2007 at our long-awaited (and at that time, not-yet-active) construction site, it was a sign of progress—a visible step toward Joshua Plaza eventually coming to fruition. A few weeks ago, we had a different sign of progress: scaffolding being taken down (below).

For a few days, all the buildings were visible. "If you want to see our buildings as they've looked for decades, do it now!" Monroe announced after church on Mother's Day. "Tomorrow the shed goes up, and when that comes down, these walls will be gone!" This was what we saw:

This area is now surrounded by a shed enclosure that will remain for the duration of the construction.

For a few days, all the buildings were visible. "If you want to see our buildings as they've looked for decades, do it now!" Monroe announced after church on Mother's Day. "Tomorrow the shed goes up, and when that comes down, these walls will be gone!" This was what we saw:
What does it take...
A New Start
Next step(s): concrete
Jacob's Ladder? No...
The beginnings of a staircase! This week, in the 2524 half of Joshua Plaza, workers installed the steel skeleton of the stairs that will lead from the first floor to the second floor.
The next step is for the concrete to be poured into the steel frame and into the corrugated steel flooring. Before too much longer, the fire escapes will no longer be the only means of access to the upper floors.
Breakthrough!
This week (the first week of February 2009), the contractor decided it was time to create the first-floor and basement hallways connecting the two buildings. Because this could not be undertaken until the structure was sufficiently stabilized, this marked a tremendously important step in the rehab/construction process.
We praise God for the safety of all the workers in the building, and ask for their continued protection. Thus far, there has not been a single injury. Given the complexity of the job and the amount of debris, this seems miraculous.
Note: Now that Joshua Plaza is under construction, the two buildings that are being merged have also been officially merged into a single address. According to the New York City Dept. of Buildings, Joshua Plaza is located at 2524 Adam Clayton Powell Jr. Blvd. (For convenience in identifying areas under construction, this blog is likely to continue to refer to street numbers 2526 and 2524 for the time being.)
We praise God for the safety of all the workers in the building, and ask for their continued protection. Thus far, there has not been a single injury. Given the complexity of the job and the amount of debris, this seems miraculous.
Windows and Walls
Name that Accomplishment
This series of photos documents some of the hard work that went into creating the beautiful sight pictured here:
And just what is it? The basement floor! It is no longer covered by tons of debris, and it has new concrete footers poured and rebar in place. The old boiler has been removed and the bedrock has been leveled out.

The boiler and the steel beams between the basement and first floor were removed by the same crew that cut out the steel staircase in the fall.

Because it turns out that the buildings are sitting are bedrock, it will not be possible to extend the basement any deeper, as had originally been planned. But wherever possible, the exposed rock has been removed. This basement will be a modern, utilitarian space—and step by step, it is beginning to take shape!
Subscribe to:
Posts (Atom)