A long way from ladders



For many months at the start of demolition and construction, the only way to get above the first floor was to climb a ladder—and depending how far/where you wanted to go, perhaps also out a window and up a fire escape. Now there is an actual stairwaynot just the poured concrete stairs that were themselves so exciting several months ago. The elevator shaft also has been built. The photograph directly above shows parts of the elevator track mechanism awaiting installation.

After the front walls, the stoops




After the successful demolition of the front walls, the sledgehammer-ers turned their attention to the job of removing the front stoops. As it turned out, they needed to resort to the use of a jackhammer instead—the bedrock that has been such an issue in digging out the basement apparently came into play here, too. But eventually both stoops were successfully removed.

...and the (front) wall came a tumblin’ down!

With help from the sledgehammer-wielding workers, the walls were removed from the fronts of 2524 and 2526. The Jesus mural partially visible in the photos above was designed and painted in the early 1990s by two young men in our congregation. This came about because groups of young men were increasingly gathering outside our church doors dealing drugs. We prayed for God’s guidance as we searched for a way to more clearly identify our corner of 146th Street as belonging to the church, and to challenge passersby with the Gospel message. When Richard Pannell and Ben Stevens (now co-pastor of King of Glory Tabernacle, Bronx, NY), suggested the idea of a mural, the idea was warmly embraced. In all the years it has been on the wall, there has never been any graffiti painted over the mural. In fact, the same young men who originally caused disturbances became the protectors of the mural—warning people from others blocks not to mess with our wall.

Salvaging a symbol

Our contractor is very accommodating about requests that might seem silly to some people. Monroe asked for the glass blocks that formed the cross above the original door (see photo below) to be removed intact and turned over to him so that they can be incorporated somewhere in the new sanctuary. The blocks that had already come out at the time this photo was taken have already been put aside.

Changes inside and out

The apartments are being framed, and plumbing and electrical lines are being run. The fire escapes at the rear of the building have been replaced. And with the completion of the concrete stairways, there is no longer a need to climb in and out of windows and up and down the fire escapes for access to the upper floors!

Scaffolding and Sheds

When scaffolding suddenly appeared in February 2007 at our long-awaited (and at that time, not-yet-active) construction site, it was a sign of progress—a visible step toward Joshua Plaza eventually coming to fruition. A few weeks ago, we had a different sign of progress: scaffolding being taken down (below).


For a few days, all the buildings were visible. "If you want to see our buildings as they've looked for decades, do it now!" Monroe announced after church on Mother's Day. "Tomorrow the shed goes up, and when that comes down, these walls will be gone!" This was what we saw:

This area is now surrounded by a shed enclosure that will remain for the duration of the construction.



What does it take...

...to finish the roof? More concrete, of course. The truck was back today, and the concrete was poured (down from above) for the third-, fourth-, and fifth-floor stairways/hallways and the rooftop.

A New Start

Last week, we reached an exciting new phase of construction: work has begun on framing the apartments!


Next step(s): concrete

A major milestone literally and figuratively—concrete has been poured for the steps from the first to second floor (seen here through the newly-created hallway connecting the two buildings). In the foreground, the floor is ready for concrete to be poured.

Jacob's Ladder? No...

The beginnings of a staircase! This week, in the 2524 half of Joshua Plaza, workers installed the steel skeleton of the stairs that will lead from the first floor to the second floor.

The next step is for the concrete to be poured into the steel frame and into the corrugated steel flooring. Before too much longer, the fire escapes will no longer be the only means of access to the upper floors.

Breakthrough!

This week (the first week of February 2009), the contractor decided it was time to create the first-floor and basement hallways connecting the two buildings. Because this could not be undertaken until the structure was sufficiently stabilized, this marked a tremendously important step in the rehab/construction process.

We praise God for the safety of all the workers in the building, and ask for their continued protection. Thus far, there has not been a single injury. Given the complexity of the job and the amount of debris, this seems miraculous.

Note: Now that Joshua Plaza is under construction, the two buildings that are being merged have also been officially merged into a single address. According to the New York City Dept. of Buildings, Joshua Plaza is located at 2524 Adam Clayton Powell Jr. Blvd. (For convenience in identifying areas under construction, this blog is likely to continue to refer to street numbers 2526 and 2524 for the time being.)

Remember those stacks of windows?

This is what the front of Joshua Plaza looks like, now that the new windows have been installed:


Windows and Walls

This (above) was the scene outside the Joshua Plaza work site after our new windows were delivered in early January. Receiving the delivery was great. But without interior stairs it is still a tremendous challenge to move supplies within the buildings. In the middle of the photo immediately below, you can see (in action) the hoist system that was used to painstakingly lift the windows from floor to floor.
As reflected in the photo above and the two below, while the windows were being installed, another crew was simultaneously installing new interior cinder block walls. (Note regarding construction costs: the cost of each block is approximately $2.00—exclusive of labor.)
This is the newly-created elevator shaft for the elevator that will run between the two (eventually-to-be-connected) buildings.

Name that Accomplishment

This series of photos documents some of the hard work that went into creating the beautiful sight pictured here:

And just what is it? The basement floor! It is no longer covered by tons of debris, and it has new concrete footers poured and rebar in place. The old boiler has been removed and the bedrock has been leveled out.


The boiler and the steel beams between the basement and first floor were removed by the same crew that cut out the steel staircase in the fall.
Because it turns out that the buildings are sitting are bedrock, it will not be possible to extend the basement any deeper, as had originally been planned. But wherever possible, the exposed rock has been removed. This basement will be a modern, utilitarian space—and step by step, it is beginning to take shape!